The intersection of Main and Wooster will remain closed until Saturday, March 23, at 1:00 pm in order to finalize water and sewer line installation within the intersection.

Next week, the contractor will continue work along North Main Street – focusing installation near the N. Main St./West Court St. intersection. As a result, West Court St. will be closed to traffic from the entrance to City Parking Lot 4 to Main St.  By the end of next week, it is anticipated that the contractor will close West Oak St, from the entrance to the Wood County Senior Center to Main St.  This closure will require the removal of on-street parking along West Oak.

The utility portion of this project is anticipated to last through the spring of 2019. Once complete, a contractor will repave the downtown.

Questions about this may be directed to the Engineering Division at 419-354-6227.