Columbia Gas update – week of July 9

Columbia Gas of Ohio has provided the City with the following tentative work schedule for the remainder of the week of July 9.

In conjunction with the Columbia Gas project, East Oak St., from North Main to North Prospect, will be closed to traffic from 7:00 am until 6:00 pm beginning Wednesday July 11 through Friday, July 13. On-street parking on East Oak St. will be restricted throughout the week as well.  Also beginning Wednesday, July 11, crews are scheduled to begin saw cutting and line installation on N. Main, from E. Oak to E. Court.  This work is planned to occur until Friday, July 13.  On Saturday, July 14, E. Court St, from Main to City Parking Lot 1, will be closed to traffic.  Access to Parking Lot 1 from Prospect will be maintained during this day closure.

Questions about the Columbia Gas project should be directed to Raquel Colon, External Affairs Specialist for Columbia Gas. Ms. Colon may be reached at rcolon@nisource.com or 419-539-6206.