Clay Street Construction

The Water Distribution and Wastewater Collection Division has completed the repairs to numerous sanitary sewer laterals in preparation of the paving portion of the Clay Street improvement project.  During this week, April 13 through 17, the existing curbs will be removed and the site will be prepared for installation of a newly poured curb.  During this work, through traffic will be prohibited and parking restrictions will be in place.  It is anticipated that the contractor will spend next week, April 20 through 24, installing new curbs.  During this portion of the project, Clay will be closed to traffic.  Milling of the existing asphalt and placement of new asphalt is anticipated to occur during the week of April 27.  Once the new asphalt has been placed, driveway approaches and ADA ramps will be installed – most likely occurring during the week of May 4.

Throughout this project, access to Clay Street will be restricted and on-street parking will be impacted.  This timeline is dependent upon weather and progress of work.